PROJECTEnquire ↗
← All projects

Custom manufacturing

Stainless steel walls and flooring for a coating enclosure

Refurbishment of corrosion-exposed enclosure components around a coating bath in Kvasiny: stainless panels, floor sections, doors and drainage integrated with the existing process equipment.

Project: 630Location: Kvasiny, CzechiaPeriod: December 2023
Process equipment refurbishment and installation

EMKO project portfolio. Supplier at the time of delivery: EMKO HOLDING s.r.o.

Photograph from the project.

Technology in its operating context.

The partial reconstruction addressed degraded galvanised walls and damaged enclosure flooring. The specification required the original dimensional interfaces to be retained and materials suited to the chemical environment. The project included measurement, fabrication documentation, preparation of stainless steel components and installation work scheduled for a production shutdown.

Scope of work

  • Measurement of the existing structure and drawings for the left and right corridor assemblies
  • Stainless floor sections, side panels, rear walls and doors
  • Anolyte and drainage channels, drainage openings and pipe interfaces
  • Dismantling, installation, cleaning and protective coating of damaged adjoining surfaces

Execution

Fabrication preparation divided the structure into installable sections for both sides of the enclosure. Bolted and welded interfaces, pipe penetrations, existing windows and the spill-containment floor had to be coordinated. The invoiced scope covers dismantling, materials, installation, cleaning, transport, documentation, start-up and production support.

Material renewal in a chemically exposed environment

The design follows an assessment of the original condition and replaces corrosion-exposed components with stainless steel. Grades 1.4401 and 1.4404, corresponding to 316 and 316L, were selected. The existing enclosure remains the process interface; the reconstruction covers specified wall and floor sections.

The technical specification distinguishes the spill-containment flooring from the side cladding. Floor panels are specified in sheet at least 3 mm thick and side panels in 2 mm sheet. The floor layout comprises two runs approximately 32 m long and 1.2 m wide.

  • The design includes 10 side panels and two rear walls with doors.

Workshop preparation and installation interfaces

The fabrication drawings separate the left and right corridor assemblies and detail floor sections, panels, doors, channels and drainage openings. The right-hand side also includes a panel with supply piping and penetration cover plates. This division allows components to be prepared before work begins on the shut-down process equipment.

The installation design connects the floor sections to the side panels and existing structure. The specification addresses joint tightness, refitting existing glass with new seals and protection of the process bath from work-related contamination. Stainless anolyte trays and associated drainage form part of the scope.

    Shutdown work and additional floor protection

    Project preparation progressed from site measurement and production drawings through procurement and fabrication to dismantling and installation in late 2023. The invoiced scope also included work-area cleaning, start-up and production support.

    A separately ordered and invoiced addition addresses the damaged adjoining floor: treatment of corrosion damage, an epoxy primer and a polyurethane topcoat. The financial range includes the main supply and this addition. It does not represent replacement of the complete coating line.

      Outcome

      Renewed booth wall and floor sections, complemented by protective treatment of the adjoining floor.

      Photograph from the project.
      Original floor and adjoining structure during the paint-line shutdown.
      Engineering 3D model of the new structure and enclosure for the cathodic dip-coating equipment.
      Completed floor and enclosure within the cathodic dip-coating equipment.
      Fitting a new stainless-steel floor section during the shutdown replacement of the structure.

      More projects in this field.

      Project photograph.

      Project 751 · Custom manufacturing

      Ammonia distributor with crosspiece

      Project location: Šaľa, Slovakia · 2024

      One grade 1.4306 stainless steel ammonia distributor, with a net shipping mass of 270 kg and documented weld examinations.

      Broader project portfolioCustom manufacture and supply

      1 complete distributorDetails →
      AI illustration.

      Project 1156 · Custom manufacturing

      Dosing screws and feeder housings

      Project location: Pardubice, Czechia · August 2026

      Four dosing screws and two twin-screw conveyor housings in grade 1.4541 stainless steel.

      EMKO PROJECTCustom manufacture and supply

      4 dosing screwsDetails →
      Project photograph.

      Project 731 · Custom manufacturing

      Reactor tray assembly refurbishment

      Project location: Šaľa, Slovakia · 2025

      Eleven reactor trays in grade 1.4466 steel: 22 halves and the associated internal components.

      Broader project portfolioAssembly refurbishment

      11 reactor traysDetails →

      A clear brief.
      A practical next step.

      Send your drawings, operating parameters or a short description of the change you need. We will review the technical interfaces and propose the next steps towards a quotation, clarifying any missing information with you.

      Discuss your requirements ↗Prepare a technical brief →+420 731 771 147info@emkoproject.cz