PROJECTEnquire ↗
← All projects

Shutdowns & maintenance

Nitration shutdown maintenance

Nitration shutdown with 17 pumps in the service schedule, a water tank and a vacuum-pump bedframe.

Project: 1142Location: Pardubice, CzechiaPeriod: August 2026
Shutdown maintenance and repairs

Supplier: EMKO PROJECT s.r.o.

Photograph from the project.

Technology in its operating context.

Shutdown maintenance of a nitration process in Pardubice covered pumps, steam and condensate systems, towers and a fan. The scope also included a water tank and a vacuum-pump bedframe; the recorded handover date is 24 August 2026.

Scope of work

  • 17 pumps in the maintenance schedule, including 10 acid pumps
  • Steam and condensate systems, towers and a fan
  • One water tank and a vacuum-pump bedframe
  • Nine work packages completed with shutdown-work handover

Pumps and auxiliary nitration equipment

The maintenance breakdown lists five pump groups totalling seventeen: groups of four and six acid pumps, two tower pumps, two pumps in another process section and three pumps in an associated operating area. These are the pumps included in the service scope.

Alongside rotating equipment, the shutdown covered steam and condensate systems, towers with a fan and one water tank. The contract linked machine maintenance with the associated process utilities.

Vacuum-pump bedframe and work structure

The vacuum-pump bedframe was a separate item, with its material and labour portions identified in the cost breakdown. The overall scope was divided into nine work packages tied to a common shutdown window.

The seventeen pumps define the maintenance scope across the individual operating sections.

Completion

The handover protocol confirms completion and handover of the shutdown work as of 24 August 2026. The scope was subsequently invoiced as one completed contract.

Outcome

Nitration shutdown work handed over across nine defined work packages.

More projects in this field.

Project photograph.

Project 1245 · Shutdowns & maintenance

Autoclave filter screen replacement

Location: Pardubice, Czechia · 2026

Shutdown installation of 80 autoclave dewatering screens, including associated installation work.

EMKO PROJECTShutdown maintenance and repairs

80 dewatering screensDetails →
AI illustration.

Project 571 · Shutdowns & maintenance

Equipment storage and handling

Recipient location: Modletice, Czechia · 2023–2024

Storage and handling of MG CG132B-12 equipment and its accessories across several invoicing periods in 2023–2024.

Broader project portfolioStorage and handling

MG CG132B-12 equipment with accessoriesDetails →

A clear brief.
A practical next step.

Send your drawings, operating parameters or a short description of the change you need. We will review the technical interfaces and propose the next steps towards a quotation, clarifying any missing information with you.