The project in context
Technology in its operating context.
Shutdown maintenance of an oxycellulose process in Pardubice combined work on flowmeters, valves, tanks, fans and pipework. The breakdown contained sixteen service items; the recorded handover date is 19 August 2026.
Scope of work
- Removal and reinstallation of flowmeters and valves
- Work on tanks, fans and alcoholisation-vessel lids
- Pipe repairs, a filter section and nitrogen lines
- Sixteen items in the agreed service scope
Instrumentation and valves during shutdown
The service scope included flowmeter work and several valve items. Some operations were explicitly defined as removal and reinstallation, covering the mechanical integration of instruments and components within the process.
The breakdown separated work groups by location and equipment. The sixteen items formed the work structure and included several separate flowmeter and valve work groups.
Vessels, piping and auxiliary parts
Other shutdown activities covered tanks, fans, alcoholisation-vessel lids, pipe repairs and removal and reinstallation of a filter section. The defined scope also included inspection work on nitrogen lines.
Associated work extended to auxiliary structural elements such as steps and doors. The contract combined interventions on process components with repairs in their immediate surroundings.
Shutdown-work handover
The handover document confirms completion and handover as of 19 August 2026. Invoicing corresponds to the overall agreed contract scope.
Outcome
Completed shutdown work on instrumentation, valves, vessels and associated piping.