01
Different locations allow different checks
FAT is factory acceptance testing at the manufacturer or integrator before shipment. It verifies agreed functions under prepared conditions, sometimes using simulated signals. SAT takes place at the installation site and checks agreed functions in the installed configuration. A successful simulation does not by itself confirm field connections or the behaviour of the complete process.
02
Test against a clear specification
Each scenario needs prerequisites, expected results, a recording method and responsibility. Agree customer participation, simulation scope, deviation handling and retesting after relevant changes. IEC 62381:2024 provides a framework for automation acceptance; each project still needs its own agreed plan. Contracts may assign different scope to the same abbreviations.
03
Handover goes beyond a signed report
The document list should match the supply: as-built information, equipment schedules, manuals, inspection results, backups and settings, plus material or calibration records where applicable. Agree software formats, licences and usage rights. Final acceptance records the status of outstanding items and responsibilities. An acceptance signature alone does not replace all other conditions for safe commissioning.
Expected engineering outputs
- Agreed FAT/SAT plan and recorded results.
- Deviation list, corrective actions and closure status.
- Organised documents matching the delivered configuration.
Technical sources and further reading
Reviewed on 18 October 2026. Product limits and applicable requirements are confirmed for each specification.