PROJECTEnquire ↗
← All projects

Process plant upgrades

Vacuum system replacement

New vacuum assembly with PP tanks, heat exchangers, piping, instrumentation and controls.

Project: 674Location: Rybitví, CzechiaPeriod: 2024
Process equipment refurbishment and installation

EMKO project portfolio. Supplier at the time of delivery: EMKO HOLDING s.r.o.

Photograph from the project.

Technology in its operating context.

Replacement of a non-functional vacuum system with a new process assembly. The scope included layout design, a support structure, polypropylene tanks, heat exchangers and piping. Workshop assembly was followed by on-site installation, instrumentation and controls, pipe insulation and operating tests.

Scope of work

  • Layout design, support structure and polypropylene tanks
  • Heat exchangers, piping, instrumentation and control components
  • Workshop assembly, installation, pipe insulation and commissioning

Execution

The work combined design, workshop assembly and installation with piping, instrumentation and insulation modifications. Measurement and control components were assigned to the specific functions of the two vacuum trains.

Two independent process circuits

The arrangement consists of two independent vacuum-pump trains. Each connects a tank, heat exchanger, vacuum pump and separator. Circulating liquid is prepared in the tank and cooled in the exchanger shell before entering the pump. A calcium-chloride brine provides cooling on the tube side.

The new layout included the support structure, polypropylene tanks and interfaces to existing utilities. The vacuum pumps and separators were supplied by the operator; the project integrated these components into the complete arrangement.

Measurement and control-valve interfaces

Each train monitors pH, level and temperature. The pH measurement controls the caustic feed through a DN15 valve; the level controls softened-water make-up through DN25. Circulating-liquid temperature downstream of the exchanger controls the brine feed through another DN25 valve.

Metal and plastic piping are combined according to the medium. The documentation specifies electrically conductive plastic for the vacuum and off-gas branches. Manual isolation and drain valves, instrument pockets and insulation on selected lines complete the arrangement.

Installation, operating tests and documentation

Workshop preparation was followed by installation within the existing facility. Operating tests and subsequent adjustments took place during summer and September 2024. An October 2024 handover is recorded in a signed protocol with defined reservations.

The documentation package covered the installed process, as-built arrangement, electrical design, electrical inspection and component records. The tests and handover relate to this specific vacuum-centre upgrade.

Outcome

The delivery provided a new supporting process arrangement for two vacuum trains, with associated piping and instrumentation. The reference covers its installation, operating verification and documented handover.

More projects in this field.

Project photograph.

Project 667 · Process plant upgrades

Acidification reactor replacement

Installation location: Lovosice, Czechia · 2024

Replacement of a 3.9 m³ reactor on a +6 m platform, including agitator assembly and modification of 15 pipe runs.

Broader project portfolioEquipment replacement, installation and connection

1 reactor with a volume of 3.9 m³Details →
Project photograph.

Project 692 · Process plant upgrades

Stainless steel tank with agitator

Installation location: Přerov, Czechia · 2024

A grade 1.4571 tank with an internal diameter of 1,950 mm, supplied in two sections and welded together during installation.

Broader project portfolioFabrication, installation and supply of a tank with agitator

1 tank with an agitatorDetails →
Project photograph.

Project 111 · Process plant upgrades

Refurbishment of formalin process heat exchangers

Export project region: Middle East · 2020–2021

Refurbishment of 17 exchangers, heaters and relief valves; separate dispatch of 11.12 t of piping assemblies.

Broader project portfolioRefurbishment and partial dispatch stages

17 exchangers in the refurbishment reportDetails →

A clear brief.
A practical next step.

Send your drawings, operating parameters or a short description of the change you need. We will review the technical interfaces and propose the next steps towards a quotation, clarifying any missing information with you.

Discuss your requirements ↗Prepare a technical brief →+420 731 771 147info@emkoproject.cz