PROJECTEnquire ↗
← All projects

Process plant upgrades

Stainless steel tank with agitator

Replacement of an original steel tank in Přerov with a new vessel and agitator included manufacturing design, workshop preparation and installation. The tank, with an internal diameter of 1,950 mm, was split into two sections and welded together on site. The design addressed a stainless-steel shell and bottom, a top cover with agitator support, and five process nozzles connecting to the existing equipment.

Project: 692Installation location: Přerov, CzechiaPeriod: 2024
Fabrication, installation and supply of a tank with agitator

EMKO project portfolio. Supplier at the time of delivery: EMKO HOLDING s.r.o.

Workshop assembly of the stainless steel tank and agitator before installation at the plant.

Technology in its operating context.

Replacement of the existing equipment required a split vessel design and interfaces to the original process pipework.

Scope of work

  • Manufacturing design of the split tank, top cover and agitator support
  • Stainless-steel parts in grade 1.4571 / AISI 316Ti
  • Workshop fabrication and trial assembly, transport and on-site completion
  • Weld map and plan for visual and liquid penetrant inspections

Execution

Workshop fabrication and trial assembly were followed by transport of the two sections, site welding, fitting of accessories and pipework connections.

A split structure for on-site assembly

The tank was designed as upper and lower assemblies, which were welded together at the installation site after transport. Manufacturing preparation covered the vessel geometry, top cover, agitator support and interfaces between the components. Workshop trial assembly took place before dispatch.

The drawings specify grade 1.4571 stainless steel, also designated AISI 316Ti, for the shell, bottom and main connection parts. The top cover and agitator support are separate steel components within the assembly. Splitting the tank allowed fabrication and completion work to be adapted to the installation conditions.

  • A vessel internal diameter of 1,950 mm, as shown on the assembly drawing.
  • The drawing specifies a 6 mm shell and an 8 mm bottom.
  • Two main shell sections, a separate top cover and an agitator support.

Five nozzles for process connections

The connection layout serves pump suction, drainage, overflow and the incoming process stream. The fifth nozzle provides a spare connection. Engineering therefore addressed nozzle positions and orientation alongside placement of the new vessel in the existing process location.

The installation scope included dismantling the original tank and removing its lining, transporting the new assembly, completing welds, fitting accessories and connecting the pipework. The work combined stainless-steel fabrication with interfaces to the existing process equipment.

  • 1 × DN 125 for pump suction.
  • 2 × DN 100 for drainage and overflow.
  • 2 × DN 150 for inlet and spare connection.
  • The drawing specifies PN 16 flanges; this designation applies to the flange connections.

Weld map and inspection procedure

A weld map was prepared for the tank with 21 identified weld positions. It specifies full visual inspection and 20% liquid penetrant inspection for the individual positions, linking inspection requirements to specific locations on the assembly.

The inspection plan covered workshop welding and completion of the tank during installation. The invoiced scope included one tank with an agitator and its installation interfaces.

  • A documented link between the construction drawing and the weld map.
  • A combination of workshop preparation, site welds and inspection before completion of the work.

Outcome

A new stainless-steel tank with an agitator replacing the original equipment within the existing process area.

More projects in this field.

Project photograph.

Project 667 · Process plant upgrades

Acidification reactor replacement

Installation location: Lovosice, Czechia · 2024

Replacement of a 3.9 m³ reactor on a +6 m platform, including agitator assembly and modification of 15 pipe runs.

Broader project portfolioEquipment replacement, installation and connection

1 reactor with a volume of 3.9 m³Details →
Project photograph.

Project 674 · Process plant upgrades

Vacuum system replacement

Location: Rybitví, Czechia · 2024

New vacuum assembly with PP tanks, heat exchangers, piping, instrumentation and controls.

Broader project portfolioProcess equipment refurbishment and installation

2 independent vacuum trainsDetails →
Project photograph.

Project 111 · Process plant upgrades

Refurbishment of formalin process heat exchangers

Export project region: Middle East · 2020–2021

Refurbishment of 17 exchangers, heaters and relief valves; separate dispatch of 11.12 t of piping assemblies.

Broader project portfolioRefurbishment and partial dispatch stages

17 exchangers in the refurbishment reportDetails →

A clear brief.
A practical next step.

Send your drawings, operating parameters or a short description of the change you need. We will review the technical interfaces and propose the next steps towards a quotation, clarifying any missing information with you.

Discuss your requirements ↗Prepare a technical brief →+420 731 771 147info@emkoproject.cz