The project in context
Technology in its operating context.
Partial stages of hydrochloric acid storage refurbishment combined engineering documentation with installation and connection of a temporary system. The scope also included operator training, instructions, and engineering for instrumentation, control and process automation. The reference covers handed-over and invoiced stages of the wider tank refurbishment project.
Scope of work
- Engineering documentation for temporary HCl storage
- Installation and connection of the temporary system, operator training
- Engineering for instrumentation, control and process automation
Execution
The project was structured into documentation approval, temporary-equipment handover, connection and training, and separate instrumentation and control engineering.
Temporary storage during tank renewal
The Pardubice project included temporary hydrochloric-acid storage as a separate stage of a wider tank-farm renewal. The scope combined detailed design documentation and installation of temporary process equipment.
Installation was followed by process connection, operating instructions and operator training. These activities are recorded in partial handover and invoicing milestones.
Measurement and control engineering
Alongside mechanical and process engineering, the project addressed instrumentation, control and automated process control. This documentation had its own approval and invoicing milestone.
Coordination between disciplines addressed the connection of storage equipment to plant operation and the planned control system.
Stages handed over in 2025
The documented scope comprises design documentation, installed temporary equipment, its process connection and operator training. The CZK 1–5 million band excluding VAT covers invoiced partial stages.
This reference presents those stages of the phased HCl-storage renewal.
Photographs from the project site
Additional photographs from May 2026 document operating pipework and valves at the ongoing refurbishment site. The stated handed-over stages and financial band continue to refer to the documented 2025 scope.
Outcome
The handed-over stages provided a temporary storage arrangement and an engineering basis for further tank renewal.